Oversized equipment installation

 

InterMax delivered and responsible for the installation of a heavy machine from Antwerp to Changzhou. It was the second time InterMax co-operated with the site for installation.
 
The machine and parts were delivered by 40’FR and 40’OT. The machine was 3.4m high and 34 tons. The entrance of the factory was only 4.5m and thus InterMax had to arrange a 80 tons mobile crane to unstuff the machine from flat rack and use low bed trailer to deliver into the factory for installation. The height was too tight and it had to be moved with care to enter the gate.
 
InterMax co-operated with thetechnicians to adjust the balance during installation, mobile crane was used to lift and adjust position of the machine. The procedure was smooth and success, client is satisfied with our operation.
 

 

 